Hello,

In quiz "Project stages and statuses", the correct answer to question #2 " Moving a project to a different Kanban stage affects its status." is "False", but when I move a project from one column to another, its status changes to "In Progress". What did I get wrong?

Best regards

Avatar
Discard

This would be True only if you have grouped the Projects by Status.

If you move 'AGR - S00066 - Sales Order' to another kanban Stage in above scenario, the Status will actually change - because the Stage actually reflects the Status.

A more obvious example would be to group Projects by Project Manager. Moving 'Renovation' from Stage 'Mark Demo' to 'Mitchell Admin' in below example will actually set the Project Manager to 'Mitchell Admin'. But - nothing else.


The question you are talking about specifically refers to Project Stages - as a dedicated 'Stage Stage': https://youtu.be/8yzslSQbg-s?t=60, thus changing the '(Project) Stage' Stage does not affect the Status:

Avatar
Discard

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!